  1. Published on: 09/02/2017 02:35 PMReported by: roving-eye



    In accordance with procedure rules, this report seeks Cabinet approval for the proposed method of procurement and the basis of tender evaluation in connection with the proposed major improvements to Southport Pier and the delegated authority for acceptance of the most advantageous bids received.

    Recommendation(s)

    1. Approve the proposed method of procurement and evaluation as set out within the report.

    2. Authorise Head of Investment & Employment to accept the most advantageous bid received in each instance if a successful grant offer is received.

    3. Subject to 2 above, authorise the Head of Regulation and Compliance to enter into contracts with the successful contractors if a successful grant offer is received.

    4. The scheme to be included in the capital programme for 2017/18 that will be presented to Council on 2 March 2017 if the grant is approved.

    5. Note the provision made within the existing pier contingency fund for works proposed of this nature

    6. It be noted that the proposal was a Key Decision but had not been included in the Council's Forward Plan of Key Decisions. Consequently, the Leader of the Council and the Chair of the Overview and Scrutiny Committee Regeneration & Skills has been consulted under Rule 27 of the Access to Information Procedure Rules of the Constitution, to the decision being made by the Cabinet as a matter of urgency on the basis that it was impracticable to defer the decision until the commencement of the next Forward Plan because of the lead in time required if a grant offer is received.

    Reasons for the Recommendation:

    Cabinet approval is required to comply with the Council’s procedure rules. The recommendations will support the receipt of the most competitive tenders for the proposed works and permit the project to progress in accordance with identified programme requirements subject to a grant offer being received.

    Alternative Options Considered and Rejected:

    All appropriate design and technical options have been considered during the scheme development and it is believed that the final proposals which have received planning and listed building consents represent the most appropriate solution.

    What will it cost and how will it be financed?

    (A) Revenue Costs
    There are no revenue implications attached to this report.

    (B) Capital Costs
    £2,875,557. An application for external funding of £1.9 million has been submitted to the Coastal Communities Fund with the remainder to be funded from the existing Pier Sinking Fund and S106 should the bid be approved.

    Capital
    Coastal Community Fund
    £1,940,000
    Bid submitted


    Pier Contingency Fund
    £900,557
    Funding in place*


    S106
    £35,000
    Funding in place
    Capital Total


    £2,875,557

    The Pier contingency fund will total £807k on 1 April 17, a further £50k will be added to the fund in March 2018 and 2019 giving a total of £907k available for capital match.

    Implications:

    The following implications of this proposal have been considered and where there are specific implications, these are set out below:

    Impact of the Proposals on Service Delivery:

    Completion of the Southport Pier project will safeguard the future of the country’s oldest and second longest seaside pier, increase the range and quality of the pier’s facilities available for visitors and increase the revenue to the Council that is generated by the Pier.

    What consultations have taken place on the proposals and when?

    The Head of Corporate Resources (FD4483/17) and Head of Regulation and Compliance (LD 3766/17) have been consulted and any comments have been incorporated into the report.

    Implementation Date for the Decision

    Following the expiry of the “call-in” period for the Minutes of the Cabinet Meeting


    Contact Officer: Mark Catherall Tel: 0151 934 2315
    Email: mark.catherall@sefton.gov.uk

    Background Papers:

    None

    Submit News to Us

    Contact us with your news. Mob/Txt 07530 315 478 southport@qnews.co.uk or Form




  2. Contact us with your news. Mob/Txt 07530 315 478 southport@qnews.co.uk or Form



    Your Comments:


  3. pedoja says:09/02/2017 08:36 PM
    What restoration is actually required?

  4. ausard2 says:10/02/2017 05:51 AM
    Can't we just sell it? then we have little
    liability and revenue coming in from
    rates etc.
    Some places I'm told have fires.???????

  5. Alikado says:10/02/2017 10:04 AM
    It's only a couple of years since millions were spent on a refurb, if it requires more millions we should let nature take its path.

  6. pedoja says:10/02/2017 10:35 AM
    Wouldn't regular maintenance be the cheaper and better option?

  7. Mr. Brightside says:10/02/2017 11:26 AM
    Quote Originally Posted by pedoja View Post
    What restoration is actually required?
    They are building stairways from the beach to the pier and replacing the shelters with cafes/retail outlets. I'm sure the proposals were publicised on here.
    Wouldn't regular maintenance be the cheaper and better option?
    Regular maintenance is carried out.

  8. mike1979 says:10/02/2017 12:25 PM
    The pier has £100,000 worth of maintenance every year.

  9. ausard2 says:10/02/2017 12:33 PM
    Just reading the article, one has to ask how many departments
    of pen pushers and quangos has this gone through to get here.
    What a lot of money money has been spent to date and thats
    before we open a tin of paint.

  10. Ric says:10/02/2017 01:03 PM
    Quote Originally Posted by mike1979 View Post
    The pier has £100,000 worth of maintenance every year.
    Don't know who told you that but it's £250 k over five years.

  11. mike1979 says:10/02/2017 01:16 PM
    Quote Originally Posted by Ric View Post
    Don't know who told you that but it's £250 k over five years.
    It came from a FOI which confirms between 2004 and 2014 just over 1 million was spent maintaining the pier. £100,000 is the average over that time.

  12. Ric says:10/02/2017 02:32 PM
    Quote Originally Posted by mike1979 View Post
    It came from a FOI which confirms between 2004 and 2014 just over 1 million was spent maintaining the pier. £100,000 is the average over that time.

    It gets £50k a year ring fenced to be spent every five years or earlier if needed. Maybe that amount included the £330 000 for the tram.

  13. Ralphy Rylance says:10/02/2017 03:47 PM
    Quote Originally Posted by ausard2 View Post
    What a lot of money money has been spent to date and thats
    before we open a tin of paint.
    Go on then, enlighten us as to how much has been spent on this to date?

    And how would you do it differently?

  14. ausard2 says:12/02/2017 12:49 PM
    Well firstly education is a helpful, to date I would on the lower
    end of guesstimates use a number of 15, 000 but that is
    lower end.
    Hey, that for how many departments to sit around and just discuss the issue.
    Do not be too concerned , because a hospital elsewhere
    has just exposed the cost of a roller blind. £23 in a store
    price to hospital £ 850. some plonker pays the bill. DOOH
    can't think ,hey this seems a little expensive.

  15. hansol2 says:13/02/2017 06:03 PM
    Quote Originally Posted by pedoja View Post
    Wouldn't regular maintenance be the cheaper and better option?
    Ever since the restoration of the Pier, people have been suggesting regular
    maintenance, to the DEAF EARS of our Councillors.

    Now its once again going to cost megga bucks to restore something that should have been maintained on a regular basis and simply because once again, our elected representative, would not and do not
    listen

  16. Ucheworgan says:19/02/2017 12:00 AM
    It should have been rebuilt in concrete and hard wood years ago. This is commonly seen on the east coast of the USA and it looks fine and weathers very well.


Custom Search
You are in: UK / North West / Southport
Find any Town in the UK, or Use UK map
Local Google MAP for Southport
Tide Predictions from NTSLF.ORG


Supporting Local Business
Supporting Local Business
Be Seen - Advertise on Qlocal

User Control Panel

Not a Member? Sign Up!

Login or Register


The Best Of Local Business

Be Seen - Advertise on Qlocal



Jobs from Indeed



UK, Local Online News Community, Forums, Chats, For Sale, Classified, Offers, Vouchers, Events, Motors Sale, Property For Sale Rent, Jobs, Hotels, Taxi, Restaurants, Pubs, Clubs, Pictures, Sports, Charities, Lost Found
southportsouthport News


Supporting Local Business
Southport, PR8
Private day nursery offering the very best in childcare for the under 5s. Open 7:30am till 6pm
WEBSITE     TEL: 01704 531256
Supporting Local Business
47 Wyre Cop Road, Scarisbrick, PR8 5LR
Pamper your pet dog. All breeds & sizes groomed. 10 years experience. Loyalty card scheme & collection - delivery service available. Discount for 2 dogs. Breeder of Chihuahuas & Amercian Cocker Spaniels
WEBSITE     TEL: 07563974613

Supporting Local Business
11 Canning Road, Southport, PR9 7SS
J.Antrobus & Son. Joinery and Building Contractors. Specialists UPVC Windows and Doors, extensions and conservatories.
WEBSITE     TEL: 01704 233664
Supporting Local Business
150 Cambridge Road, Churchtown , Southport , PR9 7LW
Johnsons Churchtown Ltd is a garage established in 1898. Mot only - £25
WEBSITE     TEL: 01704 226070


Stats: Qlocal over 1.65m unique users in 2014 (google analytics)
How We Use Cookies